For this energy project, the main focus was on coordinating several operational interfaces within a tight timeframe.
The cargo required a structured transport setup, including inland movement, temporary storage, consolidation and preparation for onward shipment via Rotterdam.
By managing the process through one central control tower, we ensured clear communication between all parties involved and kept the operational flow aligned from start to finish.
The project was completed within 14 days and covered a total volume of 700 FRT.
PICK UP LOCATION:
Mannheim, Germany
DESTINATION:
Rotterdam, Netherlands
Cargo
Diesel Engines & Accessories
INDUSTRY
Energy
SCOPE OF WORK
Control tower, pre-carriage, barge transport, OOG transport, export customs clearance, intermediate storage, consolidation, port operations & handling